Kitchen Renovation Timeline: What to Expect from Start to Finish

Kitchen Installers Team·

Kitchen Renovation Timeline: What to Expect

One of the most common questions we get is "how long will my kitchen renovation take?" Here's a realistic timeline based on our experience with 500+ IKEA kitchen installations.

Phase 1: Planning & Design (2-4 Weeks)

  • Week 1-2: Measure your kitchen, create your IKEA plan, make design decisions
  • Week 2-3: Get quotes from installers, finalize your design
  • Week 3-4: Order your IKEA kitchen, arrange financing if needed

Phase 2: Pre-Installation (1-2 Weeks)

  • IKEA delivery: Schedule delivery and verify all items are received
  • Material procurement: Order countertops (if custom, allow 2-3 weeks for fabrication)
  • Permits: Apply for any required building permits
  • Preparation: Clear kitchen, set up temporary kitchen area

Phase 3: Installation (1-2 Weeks)

  • Day 1: Old kitchen demolition and removal (if applicable)
  • Day 2-3: Plumbing and electrical rough-in work
  • Day 3-5: Cabinet assembly and installation
  • Day 5-6: Countertop installation
  • Day 6-7: Appliance installation and hookup
  • Day 7-8: Backsplash, trim, and finishing touches
  • Day 8-10: Final inspection, cleanup, and walkthrough

Total Timeline

For a standard IKEA kitchen renovation:

  • Simple galley kitchen: 3-5 weeks total (1-2 days installation)
  • Medium L-shaped kitchen: 5-7 weeks total (3-5 days installation)
  • Large U-shaped kitchen: 6-10 weeks total (5-8 days installation)

What Can Cause Delays?

  • IKEA stock issues - Check item availability before ordering
  • Permit processing - NYC DOB can take 2-8 weeks for approvals
  • Building restrictions - Co-op alteration agreements can add 2-4 weeks
  • Custom countertops - Stone fabrication typically needs 2-3 weeks
  • Change orders - Modifying your plan mid-project always adds time

Tips to Stay on Schedule

  1. Order everything at once - Don't piece together your IKEA order over multiple trips
  2. Inventory your delivery - Check every box on delivery day, not installation day
  3. Bundle services - Using one team for demolition, installation, and finishing is faster than coordinating multiple contractors
  4. Decide on finishes early - Countertop material, backsplash tile, and hardware should be selected before installation begins

Ready to plan your kitchen renovation timeline? Contact us for a free consultation and realistic project schedule. We serve all of New York and New Jersey.